Demolition Permits in Des Moines, Iowa: A Guide for Owners

Demolition Permits in Des Moines, Iowa: A Guide for Owners

Covered walkway beside a demolition site

If you own a building in Des Moines and plan to take it down, you need a demolition permit from the City before any work starts. The Permit and Development Center issues it. It asks for your site details, a protection plan, approved utility disconnections and any required department sign-offs. A separate asbestos inspection and state notification come first. This guide is for owners and project managers who live or operate outside Iowa, including in Kansas, and need to understand the sequence before hiring a contractor.

Corneliuswrecking
Plan Your Demolition Project Safely
Cornelius Wrecking provides demolition and excavation services, including certified asbestos abatement for complex projects.
Explore demolition services

TL;DR

  • Des Moines requires a demolition permit before anyone begins demolishing any building or structure, not only houses.
  • Apply through the City’s Permit and Development Center at 1200 Locust Street, (515) 283-4200, permits@dmgov.org.
  • The published fee schedule lists $50 per building for houses and accessory buildings, and $250 for other structures demolished by conventional methods.
  • Asbestos inspection, state notification and utility disconnection are not afterthoughts. They gate the permit and the schedule.
  • Closeout comes at final inspection, so the permit is not finished when the building is gone.

Table of Contents

Why a Kansas owner is reading about Des Moines

Most people who search for this are not Des Moines residents. They inherited a property, hold a vacant commercial building, manage a portfolio from another state, or are a Kansas contractor or manufacturer with a site in central Iowa. Local rules are written for someone who can walk into City Hall, and that is not you.

That changes how you plan. You need to know the whole chain of approvals up front, because every missed step costs a trip or a week of remote back and forth. We also see owners assume that the rules they know from their home jurisdiction carry over. They do not. Our own notes on how Kansas cities handle this, for example in Wichita, show how much local forms and sequencing differ even within one state. Iowa adds its own layer on top of that.

When Des Moines requires a demolition permit

The City’s Code of Ordinances, in section 26-303 of the building code, requires a permit before demolition begins on any building or structure. The rule is general. It is not limited to residential work, and it is not limited to full teardowns in the way owners often assume. The same section also treats demolition by explosives separately and attaches heavier requirements to it.

In practice, treat these as permit territory:

  • A house, duplex or townhouse coming down entirely.
  • A detached garage, barn or other accessory building.
  • A commercial or industrial building, including a warehouse or plant.
  • Any other structure, such as a silo or a freestanding tower.

Because the code speaks of any building or structure, do not decide on your own that a small or partial job is exempt. Call the Permit and Development Center and describe the scope. A short call costs nothing, and a stop-work order on a half-demolished building costs a great deal.

The Fire Prevention Bureau also describes a Fire Demolition Permit as a construction permit required before demolishing a structure. Ask the Permit and Development Center whether your project needs this alongside the building-side permit, so you do not discover a second requirement mid-project.

Who issues it and how to reach them

The City’s Permit and Development Center handles construction permitting. It sits at 1200 Locust Street, Des Moines, IA 50309. The listed phone number is (515) 283-4200 and the email is permits@dmgov.org.

If the property is in a suburb, the answer changes. West Des Moines, for instance, runs its own permit office. Confirm the property’s jurisdiction first, using the address on the tax record rather than the mailing city. A building with a Des Moines mailing address can sit in a neighboring city or in unincorporated county land, and applying to the wrong office is the most common way out-of-state owners lose a week.

What the application must contain

The code lists what the building official expects. Based on the demolition section of the building code, prepare the following:

  1. The responsible person. Name and contact details of whoever is accountable for the work, usually your demolition contractor.
  2. The property. Street address and legal description.
  3. The owner or legal agent. If you are acting for an estate or an LLC, have the authority paperwork ready.
  4. The structure. Dimensions, number of stories and construction materials.
  5. A protection plan. A drawing of the areas protected by fences, barricades, covered walkways or other protective devices, with construction details.
  6. Required approvals. Sign-offs from affected City departments or outside agencies.

The building official may ask for more, including historic-review material where the structure warrants it. Demolition by explosives brings a much longer list: operator information, preparation details, the explosives themselves, safety measures and insurance, among other items. Most projects never go near that path.

The protection plan is where applications stall

Owners tend to treat the protection plan as a formality. It is not. It must show where fences, barricades and covered walkways go and how they are built. On a building that sits against a sidewalk or a neighbor’s wall, this drawing decides whether pedestrians are safe and whether the City accepts the file. Your contractor should draft it from the actual site, not from a template.

What it costs

The City’s permit fee schedule lists demolition fees of $50 per building for townhouses, single-family dwellings, two-family dwellings and accessory buildings. Other structures cost $250 when demolished by conventional methods and $500 with explosives.

Structure Method Listed fee
Townhouse, single-family or two-family dwelling, accessory building Conventional $50 per building
Other structures (for example commercial or industrial) Conventional $250
Other structures Explosives $500

Two cautions. First, fee schedules are revised, so confirm the figure with the Permit and Development Center before you budget. Second, the permit fee is a small piece of the real cost. Asbestos inspection and abatement, utility capping, hauling, landfill tipping and site restoration dominate the total, and none of those are in the permit fee.

Do these three things before the permit is issued

The City will not issue the permit on paperwork alone. Before issuance, the code expects the sewer and water disconnection to be approved and the disposal requirements to be met. Asbestos is governed by the state and federal rules, and you should treat it as the first item on the timeline, not the last.

1. Asbestos inspection and state notification

The Iowa Department of Natural Resources states in its whole building demolition compliance guidance that federal and state law require a certified asbestos inspection before demolishing or significantly renovating a building or structure. Any regulated asbestos the inspection finds must be removed before the demolition disturbs it. The same guidance points owners to other materials that may need to come out first, such as lighting ballasts, mercury lamps, thermostats and used oil.

Then comes notification. Iowa’s workforce agency says the asbestos demolition and renovation notification must be postmarked at least 10 working days before the activity begins, and it offers an online form. Build those 10 working days into your schedule from the day the inspection report is in hand.

This is the step that most often delays a project. Pre-1980 commercial buildings, older schools, mills and industrial sites commonly hold asbestos in insulation, flooring, roofing and pipe wrap. If you run a facility like this, line up an inspector early. When abatement is needed, a contractor that holds the proper certifications and does the removal itself avoids a handoff between abatement and demolition crews. We cover that work on our asbestos abatement page.

1. Asbestos inspection and state notification — overview diagram

2. Utility disconnection

Des Moines’ code makes approved sewer and water disconnection a condition of permit issuance. Gas and electric are the other two utilities to settle. In our experience, the utility companies move on their own timeline, not yours, so request disconnections as soon as the demolition date is realistic. Ask each provider for written confirmation that service is cut and capped. The building official and your contractor will both want it, and no crew should start on a building with live gas or power.

Capped utility connections at a commercial building

3. Disposal plan

The code expects disposal requirements to be met before the permit is issued. Practically, that means knowing which landfill takes which waste, how clean concrete and metals will be recycled, and how regulated materials are manifested. Disposal rules differ by state. Our guide to Nebraska landfill disposal rules shows how much they can vary across the Midwest, so do not import assumptions from your home state.

From application to closeout

Here is the sequence we recommend for an out-of-state owner.

  1. Confirm jurisdiction from the tax parcel record.
  2. Commission the asbestos inspection and get the written report.
  3. File the state notification, allowing at least 10 working days.
  4. Request utility disconnections and collect written confirmation.
  5. Prepare the permit file: owner details, legal description, structure data, protection plan.
  6. Obtain department or agency approvals the City requires, including historic review if flagged.
  7. Submit to the Permit and Development Center and answer questions quickly.
  8. Demolish under the permit, with protections in place.
  9. Pass final inspection. The Fire Prevention Bureau says its demolition permit closes out only after the project passes final inspection.

That last point matters. Removing the structure is not the end. The City verifies the finished project, so plan for site grading, debris removal and any required backfill before you call for inspection.

How long does it take?

We cannot give you a reliable number for the City’s review time, because the sources we rely on do not publish one, and it depends on the completeness of your file and any historic or agency review. What we can say is that the longest items are usually outside the permit itself: asbestos work, the 10-working-day notice and utility disconnection. Ask the Permit and Development Center for their current turnaround when you call.

Our perspective: the permit is the easy part

We are a demolition and excavating contractor based in St. Joseph, Missouri, and we work in Missouri, Kansas, Iowa and Nebraska, plus large projects nationwide. From our side of the table, the permit application is rarely what sinks a schedule. The fee is small, the form is finite, and the City tells you what it wants.

What sinks schedules is sequencing across parties. An abatement firm finishes late, a utility has not capped a line, the demolition crew arrives and cannot start. Each handoff between companies is a place where accountability gets blurry and the owner ends up refereeing from another state.

That is why we keep the work in house. We hold OSHA and asbestos abatement certifications, we run our own crews and equipment for both demolition and excavation, and we handle hazardous material removal ourselves. One contractor owns the sequence from survey to final grade. For a remote owner, that is the difference between a project you manage and a project you chase.

Our advice: choose your contractor before you file, not after. They will draft the protection plan, line up the asbestos steps and know what the Permit and Development Center will ask. And whoever you hire, ask them to put the survey and abatement responsibilities in writing. We explain why in our piece on demolition contract terms.

— Zach

Choosing a contractor for a Des Moines job

Use these criteria when you compare bids:

  • Certifications. Ask for proof of OSHA training and asbestos abatement credentials, and check that they are current.
  • Scope clarity. The bid should say who files the permit, who pays the fees, who handles the state notification and who arranges disposal.
  • Single accountability. Count how many companies will touch the site. Fewer is easier to manage remotely.
  • Excavation capability. Foundation removal, backfill and grading are part of getting through final inspection.
  • Experience with your building type. A 1,200-square-foot house and a manufacturing plant are different jobs. For plants and large facilities, see our industrial demolition and commercial demolition services.

If you are a public agency planning municipal building removals, the procurement rules matter as much as the permit. Our page on municipal and government demolition outlines how we work with public owners, and our guide to demolition RFP requirements covers what to specify.

Working with us

We handle demolition, asbestos abatement, site clearing, concrete and asphalt removal, excavation and hauling under one roof, so your Des Moines project does not depend on a chain of subcontractors. Tell us the address, the building type and your target window, and we will walk you through the sequence above. See all of our demolition and excavating services or contact us through corneliuswrecking.com. We publish no fixed prices because each project is priced on its scope and scale.

How this compares to Kansas and Missouri

If your experience is in Kansas, expect some familiar elements and some surprises. Kansas jurisdictions also require permits for structures, but each city or county sets its own forms and timelines. For comparison, Johnson County’s unincorporated area requires a permit for demolishing all structures and has the permit expire in 180 days, a detail you should check against Des Moines’ own terms rather than assume. In Missouri, local notice and form rules vary city by city, which we outline in our Missouri demolition permit guide.

The lesson is the same everywhere: ask the local office what it wants, in writing, before you schedule crews.

FAQ

Do I need a permit to demolish a small shed or garage in Des Moines?

The City’s fee schedule lists accessory buildings among the structures with a $50 per building demolition fee, which tells you they are treated as permitted work. Because the code speaks of any building or structure, call the Permit and Development Center at (515) 283-4200 to confirm before you start, even for a small outbuilding.

How much is a permit to demolish a house in Des Moines?

The published schedule lists $50 per building for single-family and two-family dwellings and townhouses. Confirm the current figure with the City, and budget separately for asbestos inspection, utility work, hauling and disposal, which cost far more than the permit.

What does a Des Moines demolition permit application include?

It identifies the responsible person, the property address and legal description, the owner or agent, and the structure’s dimensions, stories and materials. It also includes a protection plan and any required department or agency approvals. Sewer and water disconnection must be approved and disposal requirements met before issuance.

Do I need an asbestos inspection before demolition in Iowa?

Yes. Iowa DNR guidance states that federal and state law require a certified asbestos inspection before demolishing a building or structure. A notification must also be postmarked at least 10 working days before the work begins.

When is the permit closed out?

The Fire Prevention Bureau says its demolition permit closes after the project passes final inspection. Schedule grading and cleanup before you request that inspection.

Sources