Demolition Permit in Lincoln, NE: Steps, Fees and Rules

Demolition Permit in Lincoln, NE: Steps, Fees and Rules

Commercial building secured before planned demolition

If you are taking down all or part of a building in Lincoln, Nebraska, you need a demolition permit from the City’s Building and Safety Department before any work starts. The application is not filed online. You call Building and Safety, submit a written application on the city’s form, show that the utilities are being properly abandoned, and, for most buildings other than detached one- and two-family homes, provide proof of liability insurance. This guide walks through each step in the order you will meet them, and flags the asbestos, landfill and inspection items that trip up owners and contractors.

Corneliuswrecking
Plan Demolition With Safety in Mind
Cornelius Wrecking handles residential, commercial, and industrial demolition, with OSHA and asbestos abatement certifications for complex projects.
Explore demolition services

TL;DR

  • Lincoln requires a permit to demolish, raze, tear down or remove all or part of a building, and for deconstruction done to salvage materials.
  • Demolition is not among the online permit types in Citizen Access. Call Building and Safety at 402-441-7521 for instructions.
  • The application needs a description of the building, its use, legal description and address, plus proof that utilities will be properly abandoned. Commercial and multifamily jobs also need a certificate of liability insurance naming the city.
  • Starting without a permit doubles the fees. Asbestos notification to the state is a separate step from the city permit.
  • Residential housing demolition is listed at $200.00 and a residential garage at $30.00 in the code page we reviewed. Confirm current fees when you apply.

Table of Contents

When Lincoln requires a demolition permit

The rule is broad. Under Lincoln Municipal Code 3303, a permit is required whenever someone demolishes, razes, tears down or removes all or part of a building, or carries out deconstruction to reuse salvaged materials. “Part of a building” is not a loophole for small jobs.

The code’s definition of demolition also reaches further than a wrecking ball. Removing the outer facing of a building while leaving a structural frame counts, and so does removing one or more upper stories. That matters for industrial and commercial owners planning a “strip to the frame” job, a roof-level removal or a facade replacement. If the scope takes off a story or the skin of the structure, plan on a demolition permit alongside whatever building permit the rebuild needs.

What is not a building demolition

Breaking out a parking lot, removing a slab on grade or clearing trees is a different category from tearing down a building. Those jobs can carry their own requirements, such as right-of-way work or stormwater, so ask Building and Safety when your scope sits on the line. If you also need concrete or asphalt removal, our concrete and asphalt tear-out crews scope that with the demolition so the permits line up.

Who applies and how to submit

The City of Lincoln runs most permits through Citizen Access, but its Citizen Access guidance says demolition is not listed among the permit types you can submit online. For permit types without online submittal, the city tells applicants to contact Building and Safety at 402-441-7521 for detailed instructions. Homeowners applying for themselves choose the “owner” option in Citizen Access for the permits that are online.

The city’s Permit Applications page lists a demolition permit under plan review, along with electrical, mechanical, plumbing and flood plain permits. The Building and Safety office is at 555 South 10th Street, Suite 203, per the department’s page.

In practice, the sequence looks like this:

  1. Call 402-441-7521 and tell the permit assistant you need a demolition permit. Ask for the current form and any plan-review requirements for your building type.
  2. Gather the building facts and utility documentation described below.
  3. Arrange the insurance certificate if your building is not a detached one- or two-family structure.
  4. Submit the written application and pay the fee the city quotes.
  5. Keep the site open and accessible for inspections once work begins.

If you hire a contractor, ask who is pulling the permit before you sign. Either the owner or the contractor can be the applicant in practice, but the person named carries the duties that come with it, including keeping the work available for inspection.

What the application must include

The code requires a written application on a form provided by the building official. Under Section 3303.3.2, it must give facts describing the building and its use, the legal description of the property and the street address. It must also show that provisions have been made for proper abandonment of all utilities.

Documents to have ready

Item Why it is needed
Building description and current use The city classifies the job and decides on review
Legal description and address Ties the permit to the parcel
Utility abandonment plan Required before the permit is issued
Certificate of liability insurance naming the City of Lincoln as additional insured Required for structures other than detached one- or two-family buildings
Asbestos survey results and state notification (if applicable) Separate from the city permit, but needed before work starts

The insurance requirement comes from Section 3303.5. Ask your broker early. Adding an additional insured to a policy is routine, but it still takes a few days, and it is the item most likely to stall a commercial application.

Utilities: disconnect before you demolish

Lincoln will not issue the permit until you show that the utilities are being properly abandoned. That means gas, electric, water, sewer and any communications lines are shut off, capped or disconnected according to each provider’s rules. Start these requests as soon as you have a demolition date in mind, since each utility schedules on its own timeline.

The same code section says demolition work should conform to ANSI A10.6-1990, the safety requirements for demolition. On larger projects, that translates into a written demolition plan, defined exclusion zones, dust control and a competent person on site. A contractor that can show how it handles these items will make your plan review smoother.

Fees and the cost of skipping the permit

The fee schedule in the Lincoln code lists demolition permits for residential housing, other than garages, at $200.00, and residential garage permits at $30.00. That code page is dated 2015, and fee schedules are revised from time to time, so treat those numbers as a baseline and confirm the current amount when you call. Commercial and industrial structures are not covered by those two lines, so ask the permit assistant how your building will be charged.

The penalty for skipping the step is clear. Under Section 3303.6, beginning demolition without a required permit doubles the specified fees, and it does not relieve anyone from complying with the code or from other penalties. On a $200.00 house the extra cost is small. The bigger risk is a stop-work order in the middle of a project with equipment and crews already scheduled.

Fees and the cost of skipping the permit — overview diagram

Asbestos: the step separate from the city permit

A city demolition permit does not replace asbestos compliance. Nebraska’s environmental agency explains in its demolition, renovation and asbestos guidance that the owner or operator of a facility to be demolished must submit a federal NESHAP notification 10 working days before any demolition, whether or not asbestos is present. Exempt residential structures are the exception. The notice rests on the EPA’s asbestos NESHAP rule, 40 CFR Part 61 Subpart M.

Lincoln also has local air-quality oversight. The Lincoln-Lancaster County Health Department’s asbestos fact sheet summarizes how state, federal and worker-protection rules, including the OSHA construction standard at 29 CFR 1926.1101, fit together. Contact the health department’s air quality staff before you set your schedule, since the 10-working-day clock affects your start date.

Practical points for owners and project managers:

  • Commission an asbestos inspection before you finalize the demolition contract. Older floor tile, pipe insulation, roofing, joint compound and siding are common suspects.
  • Any regulated material must be removed by properly certified abatement personnel before it is disturbed.
  • Disposal has a cost. As of January 1, 2026, the City of Lincoln charges a $27.50 handling fee per load for asbestos-containing materials at the municipal landfill. Budget for it in the abatement line, not the demolition line.

For how waste streams from a teardown are handled once they leave the site, see our guide to Nebraska landfill disposal rules for demolition waste.

Inspections and sign-off

Once the permit is issued, the work is not left alone. Section R109.1 makes all demolition work subject to inspection by the building official, and it puts the duty on the permit applicant to keep the work accessible and exposed until the inspection is approved. In plain terms: do not backfill, cover or haul away what an inspector still needs to see.

Inspector checking exposed footing at demolition site

The city’s inspector page describes building inspectors as enforcing building codes, zoning ordinances and safety regulations on buildings under demolition. Ask when you pull the permit which inspections the city expects, such as utility abandonment confirmation, and schedule them into the plan so your crew is not idle waiting on a visit.

Other permits that may apply

A demolition permit rarely travels alone. Depending on the site, you may need:

  • Electrical, mechanical or plumbing permits for capping or abandoning systems, which appear on the city’s permit applications list.
  • A flood plain permit if the parcel sits in a regulated flood area.
  • A permit for work in the public right-of-way if trucks, barricades or driveway approaches will be affected. Lincoln’s municipal code requires a permit for driveway approaches on public rights-of-way, so new curb cuts after demolition need their own approval.
  • Approvals for historic properties. Lincoln’s historic building guidance treats moving a historic structure as discouraged but preferable to demolition, and says the Planning Director may issue a certificate of allowance when a structure poses an immediate hazard to human health and safety. If your building is landmarked or in a historic district, talk to Planning before you commit to a schedule.

Small structures and light tear-outs

Sheds, decks and fences are the gray area owners ask about. Lincoln’s definition covers removing all or part of a building, so do not assume a small structure is exempt. Call Building and Safety and describe it. If the answer is that the work is minor, the practical question becomes hauling the debris. For a small tear-out and load-out, a light demolition and haul-away service handles sheds, decks and fences with the debris taken off site. Projects involving a full building, hazardous materials or heavy equipment are a different scale and call for a licensed demolition contractor.

Perspective: what we see on permitted demolition

Most permit delays we see are not about the form. They come from sequencing. The utility shutoffs are not booked, the insurance certificate lacks the additional insured wording, or the asbestos survey is done after the schedule is already set. Each is easy to fix if it is found in week one and expensive if it is found in week four.

Our view is that demolition, abatement and excavation should sit under one accountable contractor wherever possible. We are OSHA and asbestos abatement certified, and we manage hazardous material removal with our own crew and equipment, so the abatement does not wait on a separate subcontractor before demolition can begin. On industrial, energy and public projects, that closes the scheduling gaps where owners lose weeks.

Our advice for any Lincoln owner: call Building and Safety first, get the paperwork list in writing, and build your schedule backward from the 10-working-day asbestos notice. Then choose a contractor who can tell you, without hesitation, who handles each step.

— Zach

Working with a contractor on a Lincoln demolition

We handle demolition and excavation for commercial and industrial owners, along with asbestos abatement, site clearing and debris hauling, and we serve Nebraska among our regions. Public agencies planning building teardowns can see our municipal and government demolition work. Projects are priced per scope, since each building differs. To discuss a Lincoln job, start from our services page and send us the address, building type and what you know about hazardous materials.

If your project also touches Missouri, our notes on Missouri demolition permits show how different the rules can be across a state line.

A planning checklist before you call

Have these answers on hand when you phone Building and Safety, and the conversation will go faster:

  1. The street address and legal description of the parcel.
  2. Building type, size and use, and whether it is a detached one- or two-family home or something else.
  3. Whether you are demolishing the whole structure or only part, such as upper stories or exterior facing.
  4. Whether the building is historic or in a historic district.
  5. Which utilities serve it and who the providers are.
  6. Whether an asbestos inspection has been done.
  7. Who the applicant will be: owner or contractor.
  8. Your target start date, so you can work back from the 10-working-day asbestos notice.

FAQ

Can I apply for a Lincoln demolition permit online?

Not through Citizen Access. The city’s guidance says demolition is not among the online-submittal permit types, so you contact Building and Safety at 402-441-7521 for instructions. Ask which form to use and how to submit it.

Do I need insurance to get the permit?

For structures other than detached one- or two-family buildings, the code requires a certificate of liability insurance naming the City of Lincoln as an additional insured. Ask your insurer for the certificate before you apply. Detached one- and two-family structures are not subject to that requirement.

How much does a demolition permit cost in Lincoln?

The code page we reviewed lists $200.00 for residential housing other than garages and $30.00 for a residential garage. That page is dated 2015, so confirm the current amount with Building and Safety. Beginning without a permit doubles the fees.

Is asbestos testing required before demolition?

The state requires a NESHAP notification 10 working days before demolition of a covered facility whether or not asbestos is present, with an exemption for certain residential structures. Because an inspection is how you learn what regulated material is present, owners schedule it before the demolition contract is final. Ask the state environmental agency or the Lincoln-Lancaster County Health Department whether your structure is covered.

Sources